Construction and Quality Management of Prefabricated Elevated Highway Projects: A Case Study of the Elevated Section of Chongqing Expressway in Qingdao
Abstract
The prefabricated construction of urban expressway viaducts can reduce on-site wet operation and traffic occupation time, but component prefabrication, transportation, hoisting, and joint construction restrict each other, and the progress and quality are closely related. Taking the viaduct project of Chongqing Expressway in Qingdao as an example, this paper analyzes the collaborative control methods from the aspects of component supply and demand coordination, digital scheduling, night lifting, prefabrication quality, and joint construction. The research shows that the project relies on the smart beam yard and BIM+GIS platform, through the production, inspection, transportation, and erection status with the unique code of components, and forms a dynamic closed loop through "status acquisition - deviation identification - plan rearrangement - resource adjustment - result feedback"; Adjust the production scheduling and transportation batch of the Beam Yard according to the on-site erection rhythm, and take the quality acceptance as the precondition for entering the next process, which can reduce downtime and invalid stockpiling. During night construction, the risk of low illumination and fatigue operation is reduced through measurement review, mutual inspection by two persons, post rotation, and monitoring. The case shows that efficient construction needs to integrate the construction plan, quality gate control, digital scheduling, and multi-party coordination into unified management to realize the synchronization of schedule adjustment and quality control.
References
- Xu, Z., Zhang, Z., & Xu, T. (2021). Research progress of precast concrete bridge structure in 2020.Journal of Civil and Environmental Engineering, 43(S1), 288–296. (in Chinese). https://kns.cnki.net/kcms2/article/abstract?v=sb6TFb_dKppIxSQhvcqZenSlnoGWNwjjhilfpe0pLk2gaecsUpTkfKrEsY6RkocNZ_ztnG3z_YBgH-UgILIsJkQtYa72b1VCgvV2J7gQyZQq__j6PRcHqnD_5jDJ59Z5WjSA9H5tluo7FiyrLRNDZlhHQnrrnaSUAe1ACgYDUFI=&uniplatform=NZKPT
- Xu, S. (2025). Research on digital construction management in the whole process of bridge prefabrication and assembly.Urban Roads and Flood Control, (1), 174–177. (in Chinese). https://doi.org/10.16799/j.cnki.csdqyfh.240705
- Deng, L., Zhang, L., Shen, J., et al. (2025). Prefabricated elevated digital construction and management transformation.Urban Roads and Bridges and Flood Control, (3), 231–235. (in Chinese). https://doi.org/10.16799/j.cnki.csdqyfh.240566
- Jang, D. H., Roh, G. T., Jeon, C. H., & Shim, C. S. (2025). Using a construction digital twin in the optimization of crane lifting position and capacity by means of prefabricated bridge deck assembly based on simulations.Buildings, 15(3), Article 475. https://doi.org/10.3390/buildings15030475
- Wen, W., Mao, W., & Tao, S. (2022). Research on intelligent bridge construction and intelligent service in the new era.World Bridge, 50(6), 122–127. (in Chinese). https://kns.cnki.net/kcms2/article/abstract?v=sb6TFb_dKppL5weKg0uIXgzyy_he1rHYrWKdbuszmKnqiPYHF5Znz-SHRNiIX_wj_Pm4yT28rnZpLkk8xP3KRUDQhXSjduxtRvltgRzYv89NgnDOjyA6PjtPpOFS9sOYkE4_BxHKt6g6x2h0ptJUzv_ZB9s965mkzfyRxsFlMUY=&uniplatform=NZKPT
- Attanayake, U., Abudayyeh, O., Cooper, J., Mohammed, A. W., & Aktan, H. (2014). First full-depth deck-panel accelerated bridge construction project in Michigan: Constructability challenges and lessons learned.Journal of Performance of Constructed Facilities, 28(1), 128–135. https://doi.org/10.1061/(ASCE)CF.1943-5509.0000399
- Ministry of Transport. (2022). JTG/T 3654-2022 technical specification for construction of highway prefabricated concrete bridges. People's Communications Press Co., Ltd. (in Chinese). https://xxgk.mot.gov.cn/2020/jigou/glj/202209/P020220930606901816363.pdf
- Lin, S., Zhang, J., Xia, Z., et al. (2024). Research progress and prospect of prefabricated RC piers.Journal of Civil and Environmental Engineering, 46(6), 135–147. (in Chinese). https://kns.cnki.net/kcms2/article/abstract?v=sb6TFb_dKpp-bviMcoe_0nxDmkBZGNHhucVkY2NDwu45icIvQuzNCvKpGFKb-f7mei8811a_MyZdgoUwqg_nVetHeTUT5opwUqYv6vpGF8-VExl23_pf_TQ8z7z_w50bpB5wF2ztef0CPwrKXp40DgjhO5_zNfI9JEDV_gKN8LY=&uniplatform=NZKPT
- Li, J., Wang, X., Liu, D., et al. (2025). Research on application of BIM technology in scheme design of highway fabricated bridge.Journal of China and Foreign Highway, 45(1), 212–218. (in Chinese). https://doi.org/10.14048/j.issn.1671-2579.2025.01.026
- Nader, M. (2020). The new Samuel De Champlain Bridge in the accelerated bridge construction.Journal of Bridge Engineering, 25(2), Article 05019015. https://doi.org/10.1061/(ASCE)BE.1943-5592.0001515
- Zeng, M., Yin, B., Chen, G., et al. (2024). Experimental study on mechanical properties of bridge decks with UHPC joints.Highway Transportation Technology, 41(3), 125–131. (in Chinese). https://kns.cnki.net/kcms2/article/abstract?v=sb6TFb_dKpohzOdhuGJ-GQ_G-mmV5R8T_O2sX1HjSv411ZPRl2XmnaMu7UeYdyUN1WGvi4LB9DJdjnDZgO-bo14BhqvINFlvj_Mi1me7WjxoS2kk27Ya8wl3GccyF8lGYI2sZ_1GkNlx3hmKm7HnED02xehj46eqeNpBYwFbKqw=&uniplatform=NZKPT
- Fang, Z., Zhang, Y., Tan, X., et al. (2026). Experimental study on compressive stability of steel UHPC composite deck of cable stayed bridge.Engineering Mechanics, 1–13. Advance online publication. (in Chinese). https://kns.cnki.net/kcms2/article/abstract?v=sb6TFb_dKppJM2l1l9Aa28tbdBANVHNdaIXaeKTTH5tlB9BALSgAz2ZXRzOaN1Moh8OHZmJJwxAmQosXy1b2fKnsNg7efzVP56D_5oZx_UWE5lUdWi5yiCxPWKVr-9nsyqB9a1LNujNWghU_Oz_CNxauMO8DGmaoi3KBdG2h7c0=&uniplatform=NZKPT