Research Article

Excavator-Dump Truck Fleet Planning and Performance Assessment in Road Earthwork: A Case Study

Zhaohui Qin*
Suzhou University of Science and Technology

* Corresponding author: [email protected]

Abstract

From blasting and excavation to material sourcing, backfilling, haulage planning, and equipment allocation, earthwork strongly influences construction efficiency and project costs. Based on typical engineering parameters, this study establishes a representative road earthwork scenario to define a preliminary construction plan and evaluate the feasibility of the proposed excavator-dump truck combination. Specifically, rock excavation, soil excavation, and backfill shortages are quantified in bank cubic meters (BCM). The required additional soil for haulage is determined by balancing the quantities of material between the excavation and fill areas. The two transport routes are evaluated for safety, with the safer REFO route selected for subsequent analysis. Accordingly, truck payload, transport cycle time, and the required number of trips are determined. The results indicate that approximately 8,337.8 BCM of soil must be transported from Point P. With one Caterpillar 385C FS excavator and 15 CAT 725 trucks, the hauling time is about 23.23 h at 75% efficiency. Thus, it can be found that the selection of routes and operational efficiency have a significant impact on the schedule arrangement and construction planning of the earthwork project.

Keywords: earthwork; blasting; dump truck; excavation; construction planning
Published: November 3, 2026
DOI: 10.54254/2755-2721/2026.38491
Volume: ACE Vol.278
pp. 88-94
Download PDF

References

  1. Choi, G., & Han, S. (2023). Reinforcement learning-based dynamic planning of cut and fill operations for earthwork optimization.Automation in Construction, 156, 105111.
  2. Fernandes, P. G., Júnior, E. F. N., & Prata, B. D. A. (2022). Optimization of earthworks planning: A systematic mapping study.Canadian Journal of Civil Engineering, 49(12), 1781-1795.
  3. Park, S., Kim, J., Cho, K., & Seo, J. (2024). Integrating task component design in excavator-truck operation planning: Enhancing automation systems through a web-based system.Applied Sciences, 14(14), 6052.
  4. Šopić, M., Vukomanović, M., & Car-Pušić, D. (2024). Machine cost-effectiveness in earthworks: Early warning system and status of the previous work period.Sustainability, 16(17), 7294.
  5. Prasetyo, Y. T., Paradise, M., & Mukarrom, F. (2024). Productivity assessment of digging and loading equipment (Cat 330D2L) and hauling equipment (Fuso 220PS) in coal mining at PT. Bhumi Sriwijaya Perdana Coal, Musi Banyuasin Regency, South Sumatra.Indonesian Journal of Earth Sciences, 4(2).
  6. Taufiq, M. R., Putri, F. A. R., & Fanani, Y. (2024). Productivity analysis of digging, loading, and hauling equipment in overburden removal activities at PT. Anugrah Borneo Sinergy in Keramat Mina field, South Kalimantan, Indonesia.Journal of Earth and Marine Technology (JEMT), 5(1), 66-79.
  7. Mnzool, M., Almujibah, H., Bakri, M., Gaafar, A., Elhassan, A. A., & Gomaa, E. (2024). Optimization of cycle time for loading and hauling trucks in open-pit mining.Mining of Mineral Deposits, 18(1), 18-26.
  8. Liao, Z., Ding, X., Liang, M., et al. (2025). Research on the optimization of optimal blasting parameters and fragmentation control based on coal seam geological conditions.Scientific Reports, 15(1), 12238.
  9. Saadoun, A., Fredj, M., Boukarm, R., & Menacer, K. (2025). Effect of blasting parameters on rock size induced by fragmentation in quarries: A case study.ARPHA Proceedings, 9, 170-179.
  10. Lotsu, J. S., Frimpong, S., & Raza, M. A. (2026). Geometric and operational design principles for autonomous haulage systems in open-pit mining: A systematic review.Mining, 6(3), 45.