Research Article

A Systematical Review on Mechanisms of Soil Deformation Induced by Different Vertical Shaft Construction Methods

Yuzhou Liu*
City University of Hong Kong

* Corresponding author: [email protected]

Abstract

This paper reviews soil displacement induced by vertical shaft construction and compares downward and upward approaches using evidence from analytical solutions, numerical modelling and scaled tests. For downward excavation, cut-and-cover method generally produces trough-shaped surface settlement, with typical magnitudes of Smax= 0.1%~0.3%H (WhereSmaxis maximum settlement) and influence up to 1.5D(WhereDas diameter), accompanied by cantilever-type wall lateral movement peaking at mid-depth. Diaphragm-wall shafts show parabolic wall deflection (often 4~6 mm) and settlement of 8~11 mm, while groundwater drawdown may amplify deformation by 30%~50%. Vertical shaft sinking method exhibits staged deformation with a convex-to-concave transition around 0.4~0.7H. For upward methods, they can limit surface settlement (<1mm) but intensify deep soil-structure interaction and crown dislocation risk.

Keywords: Downward excavation; Upward excavation; Soil deformation; Deformation mechanisms; Numerical modeling
Published: March 9, 2026
DOI: 10.54254/2755-2721/2026.32070
Volume: ACE Vol.206
pp. 7-14
Download PDF

References

  1. Wang, J.et al. (2025) A Review of Vertical Shaft Technology and Application in Soft Soil for Urban Underground Space, Applied Sciences, 15(8), p. 3299.
  2. Hashemi, S. et al. (2025) Selection of shaft construction method, Tunnelling and Underground Space Technology, 164, p. 106654.
  3. Yang, Y.-F. et al. (2022) A new construction method for metro stations in dense urban areas in Shanghai soft ground: Open-cut shafts combined with quasi-rectangular jacking boxes, Tunnelling and Underground Space Technology, 125, p. 104530
  4. Tangjarusritaratorn, T. (2021) An implementation of soil particle transportation concept for internal erosion simulation and its application to vertical shaft construction. PhD thesis, Kyoto University.
  5. Luo, L. et al. (2025) Research on the Longitudinal Deformation of Segments Induced by Pipe-Jacking Tunneling over Existing Shield Tunnels, Buildings, 15(5), p. 1394.
  6. Li, S. et al. (2025) Use of cut-and-cover method to construct a 10 km long large-span underwater tunnel: case study, Canadian Geotechnical Journal, 62, pp. 1-16.
  7. Liu, Y. et al. (2025) Analysis of Influence of Cut-and-Cover Method on Retaining Structures and Differential Settlement in Subway Foundation Pit Construction, Applied Sciences, 15(7520), pp. 1-23.
  8. Liu, X. (2018) Study on Application of Construction Technology for Diaphragm in Underground Building, IOP Conference Series: Earth and Environmental Science, 153(052003), pp. 1-6.
  9. Schmäh, P. (2007) Vertical shaft machines. State of the art and vision, Acta Montanistica Slovaca, 12(1), pp. 208-216.
  10. Zhou, Y. et al. (2025) Analytical solution of soil deformation caused by vertical pipe jacking construction considering grouting pressure, Scientific Reports, 15(17476), pp. 1-21.
  11. Hou, M. et al. (2025) Analysis the Mechanical Response of Tunnels Under the Action of Vertical Jacking in Shield Construction and Research on Reinforcement, Buildings, 15(2321), pp. 1-16.
  12. Kondo, F. et al. (2004) Construction of three vertical shafts using upward shield machine – the Bandai–Hannan sewer tunnel construction works, Tunnelling and Underground Space Technology, 19, p. 491.
  13. Wang, L. et al. (2011) Construction behavior simulation of a hydraulic tunnel during standpipe lifting, Tunnelling and Underground Space Technology, 26, pp. 674-685.
  14. Wei, X. et al. (2022) Study of the Indoor Model Test and CEL Simulation of Jacking Force in the Vertical Tunnelling Method, Advances in Civil Engineering, 2022(3046621), pp. 1-11.
  15. Zhao, C. et al. (2023) Mechanical Properties and Numerical Analysis of Underground Continuous Wall in Underground Grain Silo Foundation Pit, Buildings, 13(293), pp. 1-20.
  16. James, A. and Kurian, B. (2022) Diaphragm wall retaining system – a simplified model for design loads, Australian Journal of Civil Engineering, 20(2), pp. 374-388.
  17. Liu, P. et al. (2025) Analysis of collapse risks under cut and cover method based on multi-state fuzzy Bayesian network, PLOS One, 20(5): e0321382.
  18. Lu, P. et al. (2025) Analysis of Strata Deformation Patterns Induced by Vertical Shaft Sinking Machine Based on Soil Deformation Zoning: A Case Study of the Zhuyuan Bailonggang Sewage Connecting Pipe Project in Shanghai, China, Applied Sciences, 15(1705), pp. 1-19.
  19. Rivera, S. et al. (2025) Study of the horizontal propagation of deformations generated by a shaft excavation, from the use of VSM machinery in soft soils in shanghai China, IOP Conference Series: Earth and Environmental Science, 1541(012011), pp. 1-9.
  20. Lu, L. et al. (2022) Mechanical Behavior of the Special Segment Structure during Upward Shield Tunnel Construction, Mathematical Problems in Engineering, 2022(8587689), pp. 1-14.
  21. Wang, X. et al. (2024) Model Design and Application for Excavation Face Stability in Upward Shield Tunneling, Buildings, 14(2514), pp. 1-23.
  22. Ding, L. et al. (2023) Study on Transverse Seismic Response Characteristics of Large Diameter Vertical Double-Layer Overlapping Pipe Jacking in the Soil-Rock Composite Stratum, Applied Sciences, 13(2343), pp. 1-14.
  23. Wu, R. et al. (2025) Axial mechanical response and deformation mechanism of vertical curved pipe jacking: Reduced-scale test and numerical simulation, Journal of Pipeline Science and Engineering, doi: 10.1016/j. jpse.2025.100354.