Research on Construction Rework Rate Control Based on BIM Technology—Taking the Caojiadu Underground Garage Project as an Example

Rongsui Yang*
Department of Architectural Engineering Institute, Wuhan University of Bioengineering, Wuhan, China

* Corresponding author: [email protected]

Abstract

The problem of rework has led to low construction efficiency and massive waste of resources in the construction industry, which is contrary to the current national “dual carbon” strategic goals. Building Information Modeling (BIM) technology can help solve this problem and achieve healthy and efficient development of the construction industry. This article takes the underground garage of Caojiadu as the research object and uses the case analysis method to explore the application of BIM technology in controlling the construction rework rate. Research has found that BIM technology can effectively reduce the occurrence of rework, save engineering costs, and improve construction efficiency; At the same time, BIM technology should strengthen its integration with emerging technologies, achieve information sharing throughout the entire life cycle of buildings, and further improve the construction quality and management level of the construction industry.

Keywords: rework rate; BIM technology; pipeline collision.
Published: July 20, 2025
DOI: 10.54254/2755-2721/2025.MH25334
Volume: ACE Vol.156
pp. 46-51
Download PDF

References

  1. Wu Zonghu. Analysis of the Impact of Rework on Construction Project Cost. Logistics Engineering and Management, 2015, 37 (07): 235-236.
  2. Statistics Department of fixed assets investment, National Bureau of Statistics. China Construction Industry Statistical Yearbook (2010). China Statistical Publishing House, 2010, 322.
  3. Atkinson, John William, Rogge, David Frederick, Haggard, Robert Lee. The field rework index: early warning for field rework and cost growth. Construction Industry Institute, Austin, 2001.
  4. Li Peipei. Research on using BIM technology to reduce the rework rate of electromechanical installation engineering. Modern Property (Mid-term), 2019, (02): 58-59.
  5. Liu Zhan, Feng Ke. Analysis of the causes, effects and countermeasures of project rework. Value Engineering, 2020, 39 (35): 241-243.
  6. Lin Zhongdong.Application of BIM technology in pipe collision detection. Fujian Construction Technology, 2024, (04): 93-95 + 127.
  7. Shao Miao, Wang Fang.Analyzing the Application of BIM Technology in Construction Project Management. Journal of Civil and Transportation Engineering, 2024, 1 (2).
  8. Application of Li Cheng. Navisworks in 3D model review of surface engineering. Oil and gas field surface engineering, 2022, 41 (01): 86-89.
  9. Sun Yuchen, Chen Qingyuan, Zhou Jiangxiang. Application of Fuzor simulation technology in construction projects. Intelligent Building and Smart City, 2016, (11): 73-75.